Kontek undertook the electrical works for the planned BM4 expansion project in addition to the existing BM1, BM2 and BM3 plants. For this project in Iran for Omya, our project partner, all project designs and calculations were prepared and approved by Kontek. Materials supplied in accordance with the approved design were installed on site, all field tests were completed and the plant was commissioned. The facility is capable of fully automated operation. All instruments required for this purpose, including sensors and magnets, were also installed, calibrated and commissioned by Kontek.
Location
Meymeh, İsfahan, İran
Project Name
Kalsiyum Karbonat Madeni Processing Plant
Date
06.11.2017 - 31.07.2018